Construction Status

Astoria Colombo is opening up a great many investment opportunities in Sri Lanka and is a notable property in Colombo real estate. Status of the project in 100% COMPLETED in 2019.
While the foundation of Astoria Colombo’s apartment, Sri Lanka is complete, you can track the status of interior, exterior and walls, as well as go through the detailed timeline that even gives you photographs of the construction process. This way, you know exactly what your investment in Sri Lanka is..

Overall Construction Status

Foundation - 100% Completed
Interior - 100% Completed
Exterior - 100% Completed
Walls - 100% Completed
  • November 2017

  • October 2017

  • September 2017

  • July 2017

  • May 2017

  • April 2017

  • March 2017

  • January 2017

  • December 2016

  • October 2016

  • September 2016

  • August 2016

  • July 2016

  • June 2016

  • March 2016

  • February 2016

  • January 2016

  • January 2016

  • November 2015

  • October 2015

  • September 2015

  • July 2015

  • June 2015

    Tower 1 and Tower 2 : The reconstruction of existing basement is finished. Tower 3 and Tower 4 : Excavation is proceeding ,the pile cushion cap and slab of basement is partly finished.
  • April 2015

  • Progress in piling - February 2015

    Structural piles – Total – 162, Completed – 99, Balance – 63,
    Secant Piles – Total – 308, Completed – 108, Balance — 200
    Structural piles – Total – 162, Completed – 99, Balance – 63,
    Secant Piles – Total – 308, Completed – 108, Balance — 200
  • March 2015

  • 2015 January 01st to 12th

  • 2014 Dec 22nd to 28th